Start a new topic

Sum of the durations without dates

Hi,

I'd like to have the duration sum to have just an estimation of the project duration if only one person is working on it,

In order to estimate the project. I don't want to set all the dates for each tasks, just have the whole number of days.


Thanks

1 Comment

Each task will be able to have an estimate when you double click on the task a property will open. 

You will see estimate and milestone appear. 


You will need to put a date for start date and finish date. You will also see a duration of the task and a work column. 

I suggest creating a baseline in your project to view planed task vs actual task. 


A summary will be found in route summary task and in your visualization page > Project overview

Login or Signup to post a comment