calendar
1 Comment
You will want to go to your Project drop down menu> project properties> then click on duration there you will be able to change your calendar days to 7 days a week. Don't forget to change your standard calendar in the calendar tab to match the project calendar.
Sandeep Mozumdar
How to change to a 7 day work week from the default 5 day work week. Creating new project and changing in the project properties are not helping