How to visualise the tracking of a project
1 Comment
Hi there,
I would have to take a look at your project file to determine if anythings missing or if there's something in the setup that could be throwing your visualizations off. Please share the project file with this email address (webinar@gantter.com) so I can take a look at it. If I can't find the problem on my own I'd recommend we hop on a gantter support call together so I can troubleshoot with you on the call while you share your screen.
To schedule please use this link, https://calendly.com/gantter
Looking forward to getting this resolved for you.
Kind Regards, Sophia

Calttla
We have created a project with tasks and resources, we have the costs and the first baseline.
when we open visualization for the overview we don't see any of the completed task. it's like if the project didn't start.
Tasks are completed and still marked as long due.
What are we missing?