Please use the following steps to create a link between two tasks: 

1. Open the "Task Properties" by double-clicking on the task in the grid.

2. Go to the "Predecessors" tab

3. Select the task to link by clicking the check box.

4. Select type of dependency under the "Dependency' column.

5. If a delay is desired, enter the number of days in the "Lag" column.

6. Click the "Save" button

You can enter the following types of dependencies:

  • Finish-to-Finish

  • Finish-to-Start

  • Start-to-Finish