Hi there, I am working on a project and would like to be able to apply a project timeline for a specific period using the Gantt chart. In other words, I am looking at hypothetically changing a project time line for any specific time. Can you please advise?
This is unique shit!!! Is there could be pay after the trial?! Don't be comical! Do just setting date option and fix plenty bugs or kick it off!
L
Laura Phillips
said
about 5 years ago
did you ever find a way, I've been trying to do the same thing and cannot get it to change dates on the gannt chart even after changing date in properties
F
Felicia Petrone
said
almost 5 years ago
The start and end dates for all tasks in the project are automatically scheduled based on the project start date and the calendars, constraints, and predecessors set on the tasks.
Please provide more details on your issue. What happens when you try to change the date?
I am including the answer to two common questions regarding dates below:
How to set a date to earlier than the project start date?
A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.
If you are looking for a time frame you can always filter your projects start and finish dates.
You can always share your project with our support team and ask for the best advise in creating your project. email info@gantter.com
C
Charles DiBetta
said
over 1 year ago
Hello Support!
I am curious. I keep seeing support cases from 3 to 5 years ago. Is Gantter still supported?
Mani Raja
said
over 1 year ago
Answer
Yes, Gantter is still supported.
D
Dennis Adams
said
8 months ago
I made a copy of my project and the date of the first Task was moved to 4/12. The original Project Start Date was 3/26, and I see this new copy of the Project has the same 3/26 start date. However, if I try to change the first Task to start on 3/26, the program refuses to accept the 3/26 date.
Is there another lock somewhere?
S
Sandeep Mozumdar
said
6 months ago
I am unable to work with a calendar of 7 days working. If I select Standard, t excludes the weekends. If I select 24Hour , then the the project duration gets squeezed to one third. If I create a ne custom Calendar, it just doesn't work at all.
Keith Sunderland
Hi there, I am working on a project and would like to be able to apply a project timeline for a specific period using the Gantt chart. In other words, I am looking at hypothetically changing a project time line for any specific time. Can you please advise?
Yes, Gantter is still supported.
8 people have this question
- Oldest First
- Popular
- Newest First
Sorted by PopularIgor Fedin
This is unique shit!!! Is there could be pay after the trial?! Don't be comical! Do just setting date option and fix plenty bugs or kick it off!
Laura Phillips
did you ever find a way, I've been trying to do the same thing and cannot get it to change dates on the gannt chart even after changing date in properties
Felicia Petrone
The start and end dates for all tasks in the project are automatically scheduled based on the project start date and the calendars, constraints, and predecessors set on the tasks.
Please provide more details on your issue. What happens when you try to change the date?
I am including the answer to two common questions regarding dates below:
How to set a date to earlier than the project start date?
A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.
If you are looking for a time frame you can always filter your projects start and finish dates.
You can always share your project with our support team and ask for the best advise in creating your project. email info@gantter.com
Charles DiBetta
Hello Support!
I am curious. I keep seeing support cases from 3 to 5 years ago. Is Gantter still supported?
Mani Raja
Yes, Gantter is still supported.
Dennis Adams
I made a copy of my project and the date of the first Task was moved to 4/12. The original Project Start Date was 3/26, and I see this new copy of the Project has the same 3/26 start date. However, if I try to change the first Task to start on 3/26, the program refuses to accept the 3/26 date.
Is there another lock somewhere?
Sandeep Mozumdar
I am unable to work with a calendar of 7 days working. If I select Standard, t excludes the weekends. If I select 24Hour , then the the project duration gets squeezed to one third. If I create a ne custom Calendar, it just doesn't work at all.
-
Creating your first schedule
-
Agenda google
-
How to mark day we will not work
-
Past Due Tasks
-
Cost columns
-
orario per la scaletta di un evento
-
Bauen
-
Company Logo
-
Printing to LARGE Plan Sheet Sizes
See all 58 topics