Adjusting printed timeline in Gantt Chart

I would like to compress the printed Gantt Chart by removing the months in which tasks are not scheduled. Is there a way to adjust the printed area of the Gantt chart?


1 person has this question
1 Comment

What is shown in your grid will be printed. If you would like to filter your dates inside the grid. 

You can double click on the start or finish column and a key filter will appear. 



You can also remove already completed task under your view drop down menu. 

For calendar you will always have about an inch space from the start of your calendar to the start of your first task. 

This can not be changed, or removed. 