duration to stay the same for a task even if I change the number of resources allocated.
Modified on: Thu, 16 Apr, 2020 at 8:52 AM
I would recommend changing the "Type" of the task to "Fixed Duration". You can adjust this on the Advanced tab of the Task Properties.