Calendar granularity

I have a project that is long running.  Days are important. Hours are not.

Is there a way to change the granularity of a calendar so when tasks are dragged / dropped they only change day by day (not hour by hour) ?

Many thanks


1 person has this question

i am making gantt chart for a supposed drug ,there are calendar signs coming in few places saying constraint applied ,how to remove constraints from calendar????/

how to remove constraints from calendar in gantt chart????

Could you please explain more of the location you are in while preforming this action. Are you inside gantter or google calendar?

Please email info@gantter.com for support

Double click on the task, and go to advance tab. There you can remove constraints.