Duration to stay the same for a task even if I change the number of resources allocated. I would recommend changing the "Type" of the task to "Fixed Duration". You can adjust this on the Advanced tab of the Task Properties.

Ways to change what task lines are viewed for printing
Here are some ideas on how to view the task lines for printing. Info in the grid will be what is printed.  You can filter your project start and finish...
Wed, 27 Aug, 2025 at 11:10 PM
How can I tell if my resources are over allocated?
Your task will be flagged in the info column if a resource assigned to this task is over-allocated.  You can also find info about over allocated resourc...
Wed, 27 Aug, 2025 at 9:38 PM
Highlighting a time period
There is two ways to "highlight" an area: You can change the Color of each task.  or you can filter the time start and finish dates.   ...
Thu, 9 Jul, 2020 at 8:37 AM
How do I switch from the google version of gantterAi to the cloud version?
All editions are linked. If you purchase a subscription in one version you will technically have access to both.  All of your files from the google and ...
Wed, 27 Aug, 2025 at 9:03 PM
How to export different types of files into gantterAi
Exporting You can transfer files by exporting them using the "Export to local Gantter file" option in the "Project" menu of the gant...