Cost of the task
3 CommentsSorted by Oldest First
HI, Is there any manual to create a new viz? or something like that?. Thanks
contact info@gantter.com for manuals.
Yes you can edit the viz tab.
You can add cost to a task by resource or by cost column. You will need to go to View drop down menu if you do not see a cost column in your grid.
You have to add a price to the resource, then when the resource is added into the task times the number of units being used to preform that task you will see a cost. The cost column you can enter in the total cost as well. I know you can see the cost in the project over view graph and in baselines.
PEI PROYECTOS
Hi, How can I see the cost of tasks? Can I add a new field with this information or seeing in the view beta?.
Thanks