FAQ

Duration to stay the same for a task even if I change the number of resources allocated. I would recommend changing the "Type" of the task to "Fixed Duration". You can adjust this on the Advanced tab of the Task Properties.

refund
Your subscription is always auto-renewed unless it is canceled before the renewal day. You can cancel your subscription by following these steps: Select t...
Mon, 13 Apr, 2020 at 11:05 AM
paypal
There is no PayPal option for online payments. If you have 10 or more users, you can start a manual invoice with an agent.
Mon, 13 Apr, 2020 at 11:06 AM
deactivate my account
Your subscription is always auto-renewed unless it is canceled before the renewal day. You can cancel your subscription by following these steps: Select t...
Mon, 13 Apr, 2020 at 11:07 AM
duration to stay the same for a task even if I change the number of resources allocated.
I would recommend changing the "Type" of the task to "Fixed Duration". You can adjust this on the Advanced tab of the Task Properties.
Thu, 16 Apr, 2020 at 8:52 AM
how do i set up summary task?
summary task is shown in the View drop down menu, as ROUTE SUMMARY TASK
Tue, 28 Apr, 2020 at 2:02 PM
How to do Critical path
The critical path is the tasks with no slack. Meaning it is the tasks that if delayed would delay the whole project. A task has a slack of one day if it can ...
Tue, 28 Apr, 2020 at 2:03 PM
Critical path
The critical path is the tasks with no slack. Meaning it is the tasks that if delayed would delay the whole project. A task has a slack of one day if it can ...
Tue, 28 Apr, 2020 at 2:03 PM
How can i show the current gantt vs baseline gantt
You will need to create a baseline. You will have to create your baseline > manage baseline Go ahead and add a baseline. I set my color for the baseline ...
Wed, 6 May, 2020 at 8:34 AM
how can I turn days into hours?
You can change duration into hours (hrs) days (days) weeks (wks) months (mons)
Thu, 21 May, 2020 at 3:12 PM
Can Gantter monitor whose causing the delay in a project?
You will find Risk, in the left toolbar of the project. This is where you can add delays to your project. I suggest pairing with a baseline and slack column...