Duration to stay the same for a task even if I change the number of resources allocated. I would recommend changing the "Type" of the task to "Fixed Duration". You can adjust this on the Advanced tab of the Task Properties.

how do i set up summary task?
summary task is shown in the View drop down menu, as ROUTE SUMMARY TASK
Tue, 28 Apr, 2020 at 2:02 PM
How to do Critical path
The critical path is the tasks with no slack. Meaning it is the tasks that if delayed would delay the whole project. A task has a slack of one day if it can ...
Tue, 28 Apr, 2020 at 2:03 PM
Critical path
The critical path is the tasks with no slack. Meaning it is the tasks that if delayed would delay the whole project. A task has a slack of one day if it can ...
Tue, 28 Apr, 2020 at 2:03 PM
How can i show the current gantt vs baseline gantt
You will need to create a baseline. You will have to create your baseline > manage baseline Go ahead and add a baseline. I set my color for the baseline ...
Wed, 6 May, 2020 at 8:34 AM
how can I turn days into hours?
You can change duration into hours (hrs) days (days) weeks (wks) months (mons)
Thu, 21 May, 2020 at 3:12 PM
Can Gantter monitor whose causing the delay in a project?
You will find Risk, in the left toolbar of the project. This is where you can add delays to your project. I suggest pairing with a baseline and slack column...
Wed, 27 May, 2020 at 11:55 AM
can we utilize the same licenses
All editions are integrated. If you are starting in Drive or Gsuite, you can export your file to Cloud edition. As well as Cloud to Drive, or Gsuite. A lice...
Wed, 27 May, 2020 at 11:59 AM
renewed without notice
Your subscription is always auto-renewed unless it is canceled before the renewal day. You can cancel your subscription by following these steps: Select th...
Fri, 29 May, 2020 at 9:41 AM
startover
Email support at info@gantter.com
Mon, 1 Jun, 2020 at 10:32 AM
Can trial period users share files?
Yes. All features are fully accessed in the trial.