Duration to stay the same for a task even if I change the number of resources allocated.
I would recommend changing the "Type" of the task to "Fixed Duration". You can adjust this on the Advanced tab of the Task Properties.
Gantter for Google relies on Google’s Share API that is sometimes not available from Google.
However, you can also share your projects directly from Google D...
Thu, 4 Jun, 2020 at 10:03 AM
Here are some ideas on how to view the task lines for printing. Info in the grid will be what is printed. You can filter your project start and finish...
Thu, 4 Jun, 2020 at 1:16 PM
There is an extension feature, please see the following link: https://gantter.freshdesk.com/support/solutions/articles/33000213253
Fri, 5 Jun, 2020 at 8:40 AM
Baselines will be in the top toolbar. This will be a stamp in time from the created baseline. Where you can see your "Actual task" start and fin...
Fri, 12 Jun, 2020 at 8:58 AM
Visualizations tab will show progress of these tasks and resources.
Fri, 12 Jun, 2020 at 9:31 AM
Your task will be flagged in the info column if the resource is over-allocated.
Your resource will be flagged under the resource tab.
And the third option t...
Fri, 12 Jun, 2020 at 9:33 AM
You will need to be the email admin to see this page. You will also have to be inside the edition that was purchased.
Fri, 12 Jun, 2020 at 9:34 AM
No gantter does not have a built-in network diagram. You will see gantters graphs under the visuzaltions tab.
Mon, 29 Jun, 2020 at 11:57 AM
There is two ways to "highlight" an area: You can change the Color of each task. or you can filter the time start and finish dates. ...
Thu, 9 Jul, 2020 at 8:37 AM
Yes, Gantter works best on Chrome browsers
Wed, 15 Jul, 2020 at 8:16 AM