Unable to load simple project XML correctly
1 Comment
Gantter automatically schedules all tasks in a project. This is similar to the "Auto Scheduled" task mode (not "Manually Scheduled") in MS Project.
After
importing the project to Gantter, all of the tasks in this project
begin on March 7, 2018 because that is the project start date and
these tasks don't have any constraints or predecessors that would
require them to be scheduled later.
To require the task to start on November 16, a constraint would need to be added to the task such as "Must Start On".
Samir Upadhye
The attached XML has a task starting 16 Nov. Yet the gantter shows everything to be starting 7 March.