How do I change the time an independent task is set for?

ex. If I say a 2-hour task's deadline is 12/2/2017 and it is to be started on 12/1/2017 it will automatically assign it to begin at 10:00 pm on 12/1/2017. I want to schedule the event for 4:oo pm and cannot seem to find a way.


Thank you,

e.


17 people have this question

How to change the dates of the tasks!!!???, when I try to set start date of the task e.g. 02/28/2018 and finish date 03/15/2018, it doesn't allow, it changes automaticall as it wants and how to select duration that it would calculate automatically when I set the start and finish dates.


4 people like this

I GOT THE SAME PROBLEM, I want to put an old cronogram but cant enter the dates

Manually you can change the time on duration column for 2hours or 3 hours, still your start date and end date will be reflecting same.

Why can't I just type a date in?? Why do you have to scroll though the calendar to select a date, it is VERY time consuming!!