How to change starting and finishing date

How to change starting and finishing date when the calender does not recognise dates in the past(only current date or dates in the future)?


Best Answer

A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.

1 Comment

Answer

A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.