How to change starting and finishing date when the calender does not recognise dates in the past(only current date or dates in the future)?
Best Answer
M
Matt Silva
said
almost 6 years ago
A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.
1 Comment
M
Matt Silva
said
almost 6 years ago
Answer
A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.
敦 渡辺
How to change starting and finishing date when the calender does not recognise dates in the past(only current date or dates in the future)?
A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.
Matt Silva
A task cannot start on a date earlier than the project start date. Please try adjusting the "Start Date" on the "Project Properties" dialog by clicking "Properties" in the "Project" menu of the Gantter editor.
-
Gantter Extensions – Getting Started
-
Can i still access the old GetSatisfaction Community posts ?
-
Time
-
Holidays calendar
-
No puedo abrir proyectos con la actualización
-
New Gantter for Google Drive doesn't open older files from Google Drive
-
Subscription link not working
-
Não consigo abrir os projetos antigos após comprar o programa
-
Pricing and sharing with customers
-
google drive and gantter
See all 251 topics