Entering new lines

Hi

I've been getting on well with Gantter but today hit a roadblock when trying to enter new lines. I keep getting an error message saying "Calendars and other project data do not allow to complete your previous action. The action has been reverted". 

It doesn't seem to be a problem in all rows, just a few.

Any ideas on what I'm doing wrong?

Thanks

Alistair


1 person has this question

That error often means that there is a circular reference among the task's predecessors which doesn't allow the project to be scheduled properly.


Please check the task predecessors to make sure there are no circular references.

Thanks

That probably makes sense. I'll give it a try.