Mark a task complete

Is there no option in Gantter to mark a task complete - say you finish it a day sooner than expected.  Is the only option to change the finish date/duration?

1 Comment

You tried changing your percent to 100% and it will mark as complete. Your view will need info column checked off to see them task completed. 