When are in the resource tab on the left side toolbar. Double click on the resource you would like to manage. In working time tab, click on the date you are editing. You will check the box override and clear to create no hours scheduled on that date. If someone is taking a day off the same steps can be made.
When are in the resource tab on the left side toolbar. Double click on the resource you would like to manage. In working time tab, click on the date you are editing. You will check the box override and clear to create no hours scheduled on that date. If someone is taking a day off the same steps can be made.
A
AJ Longo
said
about 5 years ago
Yeah this method is not working for me. Created new resource named xmas eve, Selected xmas eve resource, in working time tab selected applicable date, checked override, cleared, and saved.. Tasks still put work on this day. ??? Double checked the the resource and the working time is blank but this is not relaying to the tasks.. Deleted task, re-created, and still have work days on the date selected. Am I missing something???
S
Sébastien Gourvès
said
over 4 years ago
I've got the same problem and the solution doesn't work
M
Marissa Lapierre
said
almost 4 years ago
Click on the calendar icon on the left tab and double click on "standard" and then on the holiday date, click "clear" and it will remove the working hours, hence will be a none working day in your project.
Didier Ladroue
how to manage holidays for the ressources?
When are in the resource tab on the left side toolbar. Double click on the resource you would like to manage. In working time tab, click on the date you are editing. You will check the box override and clear to create no hours scheduled on that date. If someone is taking a day off the same steps can be made.
- Oldest First
- Popular
- Newest First
Sorted by Oldest FirstFelicia Petrone
When are in the resource tab on the left side toolbar. Double click on the resource you would like to manage. In working time tab, click on the date you are editing. You will check the box override and clear to create no hours scheduled on that date. If someone is taking a day off the same steps can be made.
AJ Longo
Yeah this method is not working for me. Created new resource named xmas eve, Selected xmas eve resource, in working time tab selected applicable date, checked override, cleared, and saved.. Tasks still put work on this day. ??? Double checked the the resource and the working time is blank but this is not relaying to the tasks.. Deleted task, re-created, and still have work days on the date selected. Am I missing something???
Sébastien Gourvès
I've got the same problem and the solution doesn't work
Marissa Lapierre
Click on the calendar icon on the left tab and double click on "standard" and then on the holiday date, click "clear" and it will remove the working hours, hence will be a none working day in your project.
-
Gantter Extensions – Getting Started
-
Can i still access the old GetSatisfaction Community posts ?
-
Time
-
Holidays calendar
-
No puedo abrir proyectos con la actualización
-
New Gantter for Google Drive doesn't open older files from Google Drive
-
Subscription link not working
-
Não consigo abrir os projetos antigos após comprar o programa
-
Pricing and sharing with customers
-
google drive and gantter
See all 251 topics