Duration and Work

There are instances where I want the duration to be longer than the hours it takes.  ex. the task itself may take 3 hours, but for a timeline I would like it slated for 2 days ..is this possible?


Best Answer

I was able to figure it out by making duration a fixed duration in the advanced tab.  


Answer

I was able to figure it out by making duration a fixed duration in the advanced tab.  

If you need the duration to be 2 days you can input that. Were you able to open the videos I sent you?