We often have scenarios were the client is responsible for a milestone but due to internal process it takes x amount of days to get to said milestone internally. Is there a way to have Duration x and Work 0 so that we don't account for it in work burn down?
1 Comment
A
Amy Adams Horvath
said
over 5 years ago
This has been answered. You need to remove the resource in order to accomplish.
Amy Adams Horvath
We often have scenarios were the client is responsible for a milestone but due to internal process it takes x amount of days to get to said milestone internally. Is there a way to have Duration x and Work 0 so that we don't account for it in work burn down?