task 2 which is on line 1 - resource is john doe and it has no predecessor
task 1 which is on line 2 - resource is john doe and it has no predecessor
You click auto-level and task 2 happens first because it's on line 1. Is there a way to get task 1 to happen first despite being on line 2? I'm use to having priorities in MS Project but Gantter doesn't seem to have this feature.
Cheers
1 Comment
F
Felicia Petrone
said
about 4 years ago
This is correct. I will send this to the team as a product request for future updates.