Planning Resources additions
1 Comment
If you have a worker 1 on your schedule you will need him on the list of recourses.
You find that 2 months later you hired someone new. You can add another recourse to that task. I suggest creating a second resource with its own calendar starting 2 months later. You would go ahead and assign a new calendar but edit this calendar to "clear working days" up until the first day of hire.
Dave Connor
If I am planning a task for the future and have resources coming available at different times, how can I set that up in Gantter? Example: A fixed work task will plan to start a month from now, with 1 full time resource. Then I plan to add a second full time resource 2 months later. I want gantter to show the expected task completion date.