Share Tasks among Plans

If I need to use the same task, with the same resource and same time planned, and the same dependencies,,,,in a plan.. is there a way we can use them in a diferent plan?


If there is a solution to that please let me know would be helpfull.

1 Comment

Hi Marco, 


Gantter Have option to Make a copy of Project with same data, Please follow the below steps. 


1) Open gantter 

2) Load project 

3) Click on Project Menu from tool bar 

4) Click on Make a Copy option from drop down 

5) Enter Project name and click on Save 

6) Project copied and will open in new tab with same data 


also you can refer steps video 

https://www.hippovideo.io/video/play/fynXk8FrSQnIy6_DDvY6QA==


Hope this help you!!!


Let us know if you need more details 


Thanks,

Gantter Support Team 