Calendar Days v. Elapsed Days
1 Comment
The duration typed into the duration column is the amount of working time for the task. This does not include weekends or holidays and depends on the calendars assigned.
3ED is not a valid input for the duration column in Gantter.
If you would like the duration on the task to be in "Elapsed Days" so that it includes weekends and holidays then this can be achieved by assigning a calendar for the task without any non-working days such as the "24-Hours" calendar.
Cameron Kinder
In the duration column. How to specify calendar days (or work days) vs Elapsed Days.
IE: The difference between:
3D and 3ED ( days and Elapsed Days )
1 person has this question