Start a new topic

View or hide subtasks - see different levels

Hello,

is there a function to see the outline level like in MS Project?  Meaning show all level 1 tasks or all level 2?


1 person has this question

Under View menu you will be able to see WBS this will give you an outline form. 

Is there any way to show just Level 1 or level 2 tasks? Just to make it easier...


Thanks!!

Here is an example of what you would see with a parent task and subtask, WBS titled.

Thank you Felicia but it doesn't answer my question to be able to filter on the different levels?  The filter capability is what I am refering to.


thanks

no not based on level.

By double clicking on a task you will open properties. There you can add notes under the note tab. 


You can create a custom column in your project > properties > column and that could be a note column if you choose to. 

Login or Signup to post a comment