Successors in Gantter

Can a successor column be added in gantter or is there a way to code the predecessor like MSP such as Start to Start or Finish to Start, etc?


4 people have this question

When you open task properties > predecessors you will see the drop down menu asking you if you want to finish to start, start to start, start to finish, or finish to finish. 

I'm missing the successor column to have an easier overview of my programme. Is it possible to have it implemented?